Wednesday, November 10, 2010

Installing doors

Renstrom and crew are now installing the interior door jams and hanging the interior doors.

Geo thermal

Rocky Mountain Geo Thermal is here to flush and fill the geothermal lines

Terrazzo

This is a picture of the terrazzo crew applying the start of the terrazzo base.

Friday, November 5, 2010

Roofing

The roofers are here today and they will be back again tomorrow to finish up all the shingles and flashing. The copper over the radius and cupola will be installed at the start of the week next week.

Basement

The drywaller made great progress in the basement today. The texure will be all complete this weekend and will hopefully be dry my monday.

Cabinet Installation

Here is a look at the cabinets as they are being installed. Renstrom and his crew should be finished installing by the end of the day. 

Thursday, November 4, 2010

Doors

The interior doors arrived on site today. Next week Renstrom and his crew will begin installing the jambs.