Here is a picture of the insulation in the interior walls
Tuesday, September 28, 2010
Insulation Begins
The spray foam insulation has begun in the upstairs bedrooms. Rich and his crew will be working through tomorrow to finish the upper and main levels. He will return next week to tie up the basement. Drywall will begin soon and then on to the finishes after drywall is complete.
Thursday, September 23, 2010
Roofing continues
The roofers are making great progress. The house is completly dried in and they are on to the shingles now. The shingles go very nicely with the stone and add a lot to the overall look of the house.
Fireplace stone
The stone arrived today for the kithchen and greatroom fireplaces. The pieces were heavy but everything ran very smooth. The masons will be installing the fireplace stone next week. The stone looks great and will create a nice feature once installed.
Tuesday, September 21, 2010
Roofing Begins
Kudu roofing arrived on site. They will begin the final dry-in today as well as shingles on the upper level.
Grading and Site Cleanup
Tim and crew are preparing the site for winter. They are bringing the dirt up around the house to almost final grade to keep the water draining away from the house. They are also cleaning and organizing the site before snow fall.
Mechanical Room
The mechanical room is coming along nicely. Josh and crew will be spending this week and the next installing and hooking up all the equipment. Currently they are hooking up the geothermal system.
Friday, September 17, 2010
Fire brick
Today the masons began the fire brick in the great room fire place. The crew also continued on the stone veneer for the east deck.
Thursday, September 16, 2010
Basement electrical
The rough in electrical is almost complete. The main panels were wired today and all that is left is the mechanical room.
Wednesday, September 15, 2010
Stonework begins on east deck!
The masons started preparing the east deck today for the stone veneer. The stone will begin to go up tomorrow and will continue throughout this week and the next. Stonework on the south side will resume next week once the trench for the water line has been backfilled.